Client project
Wybong Rail Bridge Corrosion Treatment
Overview
Doolee Construction was engaged by Rhomberg Rail to undertake protective coating remediation works to the Wybong Rail Bridge in the Hunter Valley, NSW. The project involved the inspection, assessment, and repair of deteriorated protective coating systems on critical structural steel components across a double-span rail bridge structure spanning a waterway.
Scope of work
The scope of works focused on identifying and rectifying corrosion defects affecting key structural elements, including gusset plates, connection details, and other steelwork exhibiting coating breakdown and corrosion. Following a detailed condition assessment, repair locations were prioritised in consultation with the client and marked up for remediation.
Given the bridge's location directly above a river and the presence of existing lead-based coatings, significant environmental and hazardous material controls were required throughout the project. Localised encapsulation systems were designed and installed around each repair area to contain abrasive blasting operations and prevent the release of lead-contaminated coating debris, spent garnet, and other contaminants into the surrounding environment and waterway.
Surface preparation was completed via abrasive blasting to achieve the specified cleanliness standard, followed by the application of a two-coat protective coating system comprising an aluminium-pigmented, surface-tolerant high-build epoxy and a surface-tolerant MIO (Micaceous Iron Oxide) topcoat. The selected coating system provided long-term corrosion protection while minimising disruption to rail operations.
Works were completed utilising a combination of suspended access systems, elevated work platforms and hi-rail access equipment. Several repair locations were positioned within the rail danger zone, requiring careful coordination with rail operators and completion during designated track possessions and shutdown periods to ensure the safety of both personnel and rail operations.
The successful completion of the project restored the integrity of the bridge's protective coating system, extending the service life of the asset and reducing future maintenance requirements.
Challenges
Bridge Structure Located Over Water
- All works were undertaken above a live waterway, requiring stringent environmental protection measures to prevent contamination of the river below.
- Comprehensive containment and waste management controls were implemented throughout the project.
Hazardous Lead-Based Coatings
- Existing coatings contained lead, requiring specialist hazardous material management procedures.
- Lead containment, air monitoring, waste segregation, decontamination facilities and certified disposal processes were implemented to protect personnel and the environment.
Complex Environmental Containment Requirements
- Custom encapsulation systems were installed around each repair area to contain paint debris, spent abrasive media and lead-contaminated waste.
- Controls ensured that no blasting media, paint flakes or contaminants entered the surrounding waterway.
Rail Operational Constraints
- Portions of the works were located within the rail danger zone and above active rail corridors.
- Activities were carefully planned around daily train movements, with critical works completed during tightly controlled rail shutdown and possession windows.
Specialist Access Methodologies
- Access was achieved through a combination of suspended scaffold systems, hi-rail access equipment and EWPs.
- Access methodologies were developed to safely reach difficult bridge locations while maintaining rail and environmental compliance.
Highlights
- Extension of Asset Service Life The project successfully arrested active corrosion and restored the bridge's protective coating system. The remediation works significantly extended the operational life of the structure and reduced the likelihood of future structural deterioration and maintenance interventions.