Client project
Orchard Hills Lime Tank
Overview
Doolee Construction carried out the internal remediation and protective coating of the Orchard Hills Lime Tank at Sydney Water’s Orchard Hills Water Filtration Plant for client Programmed, delivering the $800,000 blast and paint project between October 25 and November 25.
Scope of work
The works involved refurbishment of a cylindrical lime tank approximately 3.5 m deep and 2.0 m in diameter, including dry grit blasting of the tank walls and floor to remove degraded concrete and achieve a CSP 1–CSP 3 surface profile. Blasting methodology was adapted on-site, transitioning from 30/60 to 20/40 garnet to suit substrate conditions and meet specification requirements. Following preparation, a Sika coating system comprising Sikafloor®-161 primer and Sikagard®-63N intermediate and top coats was applied to enhance durability and extend the asset’s service life. All works were completed within a confined space environment under strict safety protocols, including dedicated rescue capability, with careful coordination around existing mixing and QA equipment to ensure successful delivery within an operational water treatment facility.
Challenges
- This project involved the internal remediation and protective coating of a lime tank within Sydney Water’s water filtration plant. The cylindrical tank measured approximately 3.5 m deep with a 2.0 m diameter and required refurbishment to restore the concrete substrate and extend the asset’s service life.
- The tank walls and floor were dry grit blasted to remove degraded and corroded concrete and to achieve the specified surface profile of CSP 1–CSP 3. Initial blasting was undertaken using 30/60 garnet; however, due to the condition and hardness of the substrate, blasting media was revised to 20/40 garnet to achieve the required surface preparation standard.
- Following surface preparation, a protective coating system was applied, comprising Sikafloor®-161 primer and Sikagard®-63N intermediate and top coats, in accordance with manufacturer specifications and project requirements.
- All works were completed within a confined space environment, with full confined space entry procedures in place, including a dedicated confined space rescue capability and associated safety equipment for the duration of the project. Works were carefully sequenced to accommodate existing mixing and QA equipment located within the tank.
Highlights
- Successful remediation and coating of a critical Sydney Water asset within an operational water treatment facility demanding a strong focus on safety, quality, and coordination with site operations.
- High-quality surface preparation achieved across tank walls and floor, meeting specified CSP 1–CSP 3 profile.
- Adaptive blasting methodology implemented by revising garnet size to suit site conditions and achieve required outcomes.
- Application of a Sika coating system to enhance durability and long-term asset protection.
- Safe execution of works in a confined space, supported by trained personnel, rescue capability, and compliant systems of work.
- Effective coordination of works around existing mixing and QA equipment within the tank.