Project description
As an experienced mining contractor , Doolee was engaged to deliver the bulk earthworks package for the NSR Stage 2 enabling works. The project involved the construction of a service corridor, permanent and temporary loop roads, laydown areas, pad preparation for concrete pours and an Event Pond. In total there was 30,000m2 cut and 55,000m2 of fill.
The project also included the removal of 8 km of redundant services piping and the management and conditioning of material from several borrow pits. The enabling package centred on bulk earthworks, part of our broader civil construction offering.
The execution of the NSR enabling package relied on
Scope inclusions
- Bulk earthworks: Cut 30,000m3 and fill 55,000m3
- Pavement build‑up of temporary and permanent ring roads
- Construction of event pond
- Borrow pit management and conditioning of material
- Detailed pad preparation for concrete works
- Traffic management
- Removal of 8km of piping from previous services corridor
Challenges & Highlights
Challenges
- Fast track programme
- Working within a live mine processing plant
- Machinery size restriction due to tight work areas and public roads
- Removal of 8km of piping
Highlights
- Project delivered on time
- Great teamwork regarding SIMOPS in tight work areas
- Job delivered safely
- QA for the work completed