Project description
Doolee’s scope included all earthworks, civil, concrete and piping, required to complete the works.
- Saline Dam #3 construction, including overflow pit.
- Lining installation
- Expansion of an existing Scour Pit.
- Removal of existing pump structure and piping
- Removal and reconstruction of road crossings
- Access track construction
- Service corridor construction
Our expertise in
Scope inclusions
- Clearing of Heavy Vegetation – approx 49,000m2 including preparation of area, mulching and hauling to stocking
- Bulk Earthworks – win, condition, haul (2km) and placement on embarkment 45,000m3 of fill
- Supply and Installation of Over 20,000 m² of HDPE Lining – 2-layer System, including preparation, welding, testing, and QA documentation
- Construction of Reinforced Concrete Structures approx. 100m3 in total – including pump footings, pipe guides, sump, and electrical substation footings
- Road Crossings – removal of crossings, relocation of live services, installation of culverts and pavement build-up
- HDPE Piping – through the dam wall to pump stations
Scope inclusions
Challenges
- Staging of works to allow access to work areas
- Unsuitable material existing on work fronts
- Challenging weather conditions
Highlights
- Multi-faceted project
- Quality of work completed
- Works completed safely