Project Description
Doolee were engaged by Fortescue to construct a new gymnasium facility at the Pilbara Cloudbreak mine site. The gym is located in the Pilbara region of Western Australia, approximately 150km North of Newman
(22.20 S / 119.25 E) within the East Pilbara Shire. The facility has an internal floor area of 1530m2 and
includes the following main features;
- 184m2 of studios space.
- An indoor multipurpose sports court.
- Heavy weight and gym area.
- Sauna and ice shower facility.
- Toilet and shower facilities.
- Office and reception area.
Scope Inclusions
- Bulk Earthworks and quarrying of structural filling material.
- All external service infrastructure including Electrical, Hydraulic and Civil stormwater.
- Concrete supply and batching.
- Concrete placement of footings and slab.
- Supply and erection of structural steel.
- Supply and installation of Bondor cladding.
- Mechanical supply and installation of HVAC equipment and ducting.
- Supply and installation of electrical distribution, communications, lighting, CCTV and dry fire.
- Supply and installation of hot and cold water, sanitary service and fixtures.
- Architectural fit out including joinery, floor finishes, indoor pitch and netting, loose furniture and fixtures and fittings.
- External works including civil works, footpaths, fencing and rock pitching.
- Testing, verification and commissioning.
Scope Inclusions
Challenges
- There was no nearby facility for concrete supply, a mobile concrete batching plant had to be set up to supply all the concrete requirements.
- There was no nearby stockpile of structural filling, so all structural filling had to be quarried and transported to site.
- The new project was in an existing mine site camp which can cause logistics issues for construction.
- The site was a brown fields site which meant all existing services had to be located and verified prior to construction.
- The flooring in the heavy weights section of the gym had multiple different set-downs in the concrete slabs to cater for a seamless floor finish between the different floor types.
Highlights
- A concrete batching plant was mobilised and commissioned to supply 440m3 of concrete for the project.
- Bulk earthworks and quarrying of 3200m3 of structural filling required wet and dry hire options across loaders, dump trucks and the mobile concrete batching plant.
- The project was completed within 6 months of mobilising to site slightly ahead of the contract programme.