Project description
The project involved the construction of a service corridor with the installation and commissioning of 13 primary lines, each 1km in length. Services included Tails, Seepage, Potable Water, Sewer, Saline, and Decant lines. The site was adjacent to a live mine processing facility and mining workshops.
The works included large-scale earthworks cut and fill, installation of culverts, pouring in situ concrete road crossings, staging of cutovers and removal of pre-existing services corridor. Doolee undertook the civil aspects of the project working closely with NSR and other mine stakeholders to ensure smooth completion and minimum disruption to operations and processing within the mine. The project started in March 2024 with completion in August 2024.
Scope inclusions
- Bulk earthworks cut and fill
- Construction of temporary and permanent ring roads
- Installation of temporary and permanent valve stations
- Placement of 240 culverts and lids
- In situ concrete works such as road crossings, retaining walls, thrust blocks and pedestals
- Removal of existing services corridor piping
Our team delivered comprehensive piping solutions, utilising
Scope inclusions
Challenges
- Fast track programme
- Working within a live mine processing plant
- Staging of works and cutovers to minimise disruption within the plant
- Complicated tie-in locations with existing lines
Highlights
- Project delivered on time
- No issues with leakage on any pipes, flanges or valves
- Great teamwork regarding SIMOPS in tight work areas
Our team provided











