Project description
The project involved the install and commissioning of three new water tanks and ancillary equipment to the Newman Water Treatment Plant. The site was located on a sloped area adjacent to the existing plant which coincided with a large earthworks development to create a level pad for the additional tanks. Doolee undertook the civil aspects of this project working closely with Downer and BHP to complete this fast‑tracked project. The project started in February 2024 with completion expected in Q3 2024.
Scope inclusions
- Slab demolition
- Detailed earthworks
- 16m diameter tank ring beam
- Various concrete works such as slabs, retaining wall and pedestals
- Trenching, laying conduit and backfilling for electrical conduits
- Rock protection
Challenges & Highlights
Challenges
- Fast track programme
- Working within a live water treatment plant
- Sloped site with high‑voltage power lines
Highlights
- Critical path items on track
- 20000 tonne stone import
- 3 ring beams excavated, formed, and poured within 10 days


















